A good renovation budget template lists every room and every item as a row, with columns for scope, quantity, unit, rate, estimated cost, quoted cost, GST, amount paid, balance and status. Add separate lines for design, demolition, debris removal and cleaning, then a 10–15% contingency on the total. Track quotations in the same sheet so you compare line by line, and update it after every payment.
In this guide
Searches for renovation spreadsheets and trackers keep rising, and for good reason: most budget overruns come from items nobody wrote down. This template is the same structure we use when estimating a project. Pair it with our home renovation guide, our interior cost calculator and how to compare quotations.
The template columns
| Column | What to enter |
|---|---|
| Room | Living, kitchen, master bedroom, bathroom 1 and so on |
| Item | Wardrobe, false ceiling, repaint, rewiring, tiles |
| Scope | A short description: size, finish, brand |
| Quantity and unit | e.g. 63 sq ft, 12 points, 1 no. |
| Rate | Per unit, from a rate card or quotation |
| Estimated cost | Quantity × rate |
| Quoted cost | From the vendor you select |
| GST | Rate and amount, if not included |
| Paid | Running total of payments |
| Balance | Quoted + GST − paid |
| Vendor and due date | Who, and when the next payment is due |
| Status | Not started, ordered, in progress, done, snag |
Sample filled-in 2BHK budget
| Room | Item | Quantity | Rate (before GST) | Estimate |
|---|---|---|---|---|
| Master bedroom | Laminate wardrobe with loft | 63 sq ft | ₹2,000–2,500 | ₹1.26–1.58 lakh |
| Second bedroom | Laminate wardrobe with loft | 45 sq ft | ₹2,000–2,500 | ₹90,000–1.13 lakh |
| Living | TV unit | 35 sq ft | ₹2,000–2,500 | ₹70,000–88,000 |
| Living + bedrooms | Gypsum false ceiling | 350 sq ft | ₹90–110 | ₹31,500–38,500 |
| Foyer | Shoe unit | 20 sq ft | ₹2,000–2,500 | ₹40,000–50,000 |
| Whole home | Painting | As measured | From quotation | — |
| Kitchen | Modular kitchen | As designed | See kitchen cost guide | — |
| Contingency | 10–15% of total | — | — | — |
Joinery and ceiling rates are ModScale’s 2026 rates before GST; sizes follow the typical sizes used in our calculator. Kitchen budgets are in modular kitchen price per sq ft.

Lines people forget
- Design or 3D visualisation fees, if charged separately.
- Demolition, debris removal and society lift or deposit charges.
- Electrical and plumbing changes before carpentry.
- Hardware upgrades (soft-close hinges, tandem drawers, lift-ups).
- Appliances: chimney, hob, built-in oven, dishwasher.
- Curtains, rugs, lights and loose furniture.
- Deep cleaning before move-in.
- GST on every line where it applies.
Add one row per payment milestone as well. It keeps cash flow visible and makes it easy to match payments with work done.
How to use the sheet during the project
- Fill estimates before asking for quotes; it shows where quotes differ.
- Enter each quotation in its own column so you can compare by item.
- Lock the scope before work starts; record any change as a new row with its cost.
- Update paid and balance after every payment.
- Use the status column for snags at handover (see handover snag list).

Frequently asked questions
What should a home renovation budget template include?
Rows for every room and item, and columns for scope, quantity, rate, estimate, quoted cost, GST, paid, balance, vendor and status, plus a contingency line.
How much contingency should I add?
About 10–15% of the total, more for older homes.
Can I use this in Google Sheets or Excel?
Yes. Copy the column headings into a new sheet and add one row per item.
How do I estimate wardrobe costs in the sheet?
Multiply the front area including loft by the rate. ModScale’s 2026 rates are ₹2,000–2,500 per sq ft for laminate, ₹2,500–3,000 for acrylic and ₹3,500–4,000 for sliding systems, before GST.
Should GST be a separate column?
Yes, unless every quote you compare already includes it.
How often should I update the budget?
After every payment and every scope change, and at least weekly during work.